A large-scale initiative dedicated to sustainable pineapple cultivation, supporting Malaysia’s agricultural economy.
Located in the Agropolitan Gana area of Kota Marudu, IPR-INTAN is a pioneering 500-acre MD2 Pineapple project in partnership with the Economic Ministry and Lembaga Industri Getah Sabah (LIGS). This project underscores our commitment to sustainable development and economic empowerment through large-scale pineapple cultivation.
0

acres planted

A significant portion of the project area is now fully cultivated, with the rest planned for further expansion.

0 M

pineapple plants

Achieved by August 2024, reflecting the density and scope of the planting.

Project Progress

August 2023
PHASE 1
Site Inspection & Preparation

Initial site inspection, site clearance & soil sampling for every blocks

August 2023
PHASE 1
Planting

Planting process constantly going on. Up to August 2024, total of 2, 700, 000 plants have been planted. An acre of land has the total of 15, 000 plants.  

November 2023
PHASE 1
Weed & Pest Control

Weed control are done by manual, meanwhile pest and fungi control are done as recommended by appointed agronomists.

January 2024
PHASE 1
Fertilization

Fertilization process are done following the schedule provided by the appointed agronomists. 

May 2024
PHASE 1
Forcing Programe

Forcing programe are implemented to 9-months old plantation blocks. This is to ensue synchronized flowering. This is followed by pos-forcing fertilization. 

Gallery

Site Inspection

Early site inspection & Soil sampling

Site Inspection

Clearing site & soil sampling for each plantation block

Road and Drainage Construction

Building road & drainage alongside with soil land preparation

Road & Drainage Construction

Drainage & road sketching

Road & Drainage Construction

Constructing drainage & road alongside with weed poisoning around plantation site

Receiving Fist Batch of Seedlings

Inspection by Biosecurity Division, Department of Agriculture Sabah before being sent to IPR Gana

Seedlings Plantation

First plantation are done on August 2023

Fertilization

Fertilization process are held as recommended by agronomist

100 days after Forcing

Watch the Blooming Stages of Our Pineapples Unfold – Click the Arrow to See the Progress!

50 Days
After Forcing
60 Days
After Forcing
70 Days
After Forcing
80 Days
After Forcing
90 Days
After Forcing
100 Days
After Forcing

Visit from Ministry of Economy, Agriculture Division

Visit by Datin Zaeidah Mohamed Esa, Director